江铜贵冶转炉渣选矿二期工程调试与技改
The Debugging and Innovation of the Convertor Slag Floatation Project in Guixi Smeltery
-
摘要: 江西铜业公司贵溪冶炼厂二期转炉渣选矿工程于2000年6月13日投产, 由于设计及设备选型等诸多因素的影响, 主要生产指标未能达到设计要求, 后经一年多的调试与改造, 工艺流程日趋完善, 主要生产指标达到或超过设计标准, 取得了较好的经济效益。Abstract: The convertor slag floatation project was put into production in Guixi Smeltery on June 13, 2000.The main productive targets haven't reached the demand of design because of the influence of design and the selection of equipment.The process become perfect and the main targets reach the demand of design, also it makes good economic benefits after debugging and innovating the process.This paper introduce the measures and experiences.